أسئلة شائعة حول OEM/ODM: الحد الأدنى للطلب، وقت التسليم، أخذ العينات والشحن

OEM Apparel Order Checklist: 12 Steps From First Enquiry to Delivery

Quick answer: An OEM apparel order has twelve steps, but only four are decision gates: tech pack sign-off, proto approval, size-set approval and pre-production sample approval. Everything that goes wrong later traces back to one of those four being waved through. The checklist below tells you what to hold at each gate.

This is written for a brand placing a first or second order — usually 300 to 3,000 pieces across two or three styles — with a manufacturer in Guangzhou or elsewhere in southern China. It assumes you have a design idea and no established process.

Why a checklist, and not a timeline

Timelines tell you when things should happen. Checklists tell you what must be true before you allow the next step to start. Factories generally deliver on schedule when the inputs are complete and slip when they are not, and almost every delay we see on a first order comes from a decision that was made late or made twice.

The twelve steps, and what closes each one

#StepWhat you must produce or confirmGate?
1Define the productCategory, fit intent, fabric direction, target FOB, target quantity—
2Screen manufacturersThree to five candidates who genuinely run your category—
3Send an enquiry briefOne-page brief: style description, quantity, target price, delivery window—
4Review quotationsLine-by-line comparison, not a single FOB number—
5Agree commercial termsMOQ, payment structure, Incoterm, lead time, sampling cost—
6Write the tech packSketch, measurements, materials, construction, labels, packagingGate 1
7Proto sampleOne sample to prove the concept and the constructionGate 2
8Fit sample and fit roundsSample on a live fit model, comments consolidated in one pass—
9Size setOne sample per size, graded from the approved fitGate 3
10Pre-production sampleSample made on bulk fabric with bulk trimsGate 4
11Bulk production and inspectionIn-line check plus final AQL inspection report—
12Shipment and reconciliationPacking list, commercial invoice, shipping docs, balance payment—

The four gates, and what to hold at each

Gate 1 — Tech pack sign-off

A tech pack is not a design file. It is the document that decides what "correct" means for the factory. Sign it off only when it contains measurements with tolerances, named fabrics with a supplier or a reference, stitch and seam specification, and an explicit acceptance standard. If any of those four is missing, production will improvise, and improvisation is what you will pay to correct later.

The most common failure at this gate is specifying measurement points without tolerance. A waistband specified as 68 cm with no tolerance will be argued about. A waistband specified as 68 cm ± 1 cm is a decision.

Gate 2 — Proto approval

The proto exists to prove the construction, not the fit. Approve it on construction and silhouette, and resist the temptation to also use it to finalise fit — that is what the fit sample is for. Mixing the two is how brands end up with five rounds instead of two.

Gate 3 — Size-set approval

The size set is where grading is proven. Approve it by measuring every size against the grade rule, not by trying on the middle size. A grade rule that works on a legging will not automatically work on a jumpsuit with a fixed torso length, and a size set is the cheapest place to discover that.

Gate 4 — Pre-production sample

The PP sample must be made from bulk fabric with bulk trims. Approving a PP sample made from sampling stock is one of the most expensive approvals a buyer can give, because the fabric is the one variable the sample was supposed to test.

What to prepare before you send the first enquiry

Buyers who send the most useful enquiry get the most useful quotation. Prepare:

  • A one-page product description — category, silhouette, fabric direction, colour count.
  • A quantity estimate per style and per colour, not a total.
  • A target FOB that you know is realistic for the category.
  • A launch date, stated as the date you need goods in hand, not the date you would like them.
  • Any non-negotiable — certification, a named fabric mill, a packaging standard.

That is roughly one page. It is enough for a manufacturer to tell you whether the order is feasible and what the real risks are, which is more valuable at this stage than a precise price.

The three things buyers most often get wrong

MistakeWhat it costsHow to avoid it
Approving a sample visually onlyBulk measurement disputes, rework, air freightMeasure the approved sample and write the numbers into the tech pack
Consolidating fit comments across several roundsExtra sampling rounds, lost weeksCollect comments once, prioritise them, send as a single marked set
Treating the quotation as one numberPaying for scope you did not ask for, or missing scope you didCompare quotations line by line — fabric, CM, trims, packaging, freight

A realistic first-order calendar

For a first order of 300 to 1,000 pieces across two styles in activewear or down outerwear, plan for 90 to 120 days from tech pack sign-off to goods in hand. Of that, roughly 15 to 20 days is sampling and approval, 30 to 45 days is bulk production, and the balance is material lead time and shipping. Compressing sampling is the most common way brands try to save time, and the most common reason the order arrives wrong.

Frequently asked questions

How long does a first OEM order take from enquiry to delivery?

Plan 100 to 130 days in total: three to four weeks of enquiry, quotation and tech pack work, three to four weeks of sampling and approval, four to six weeks of bulk production, and shipping. Repeat orders with an established tech pack run considerably shorter because the sampling stages collapse.

Do I need a tech pack before I approach a factory?

No. A one-page brief is enough to start a conversation and get a feasibility opinion. But you do need a tech pack before sampling begins, and you should expect to write it with input from the factory on construction feasibility.

How many sample rounds should I budget for?

Two fit rounds on a first style is normal, three is common on structured outerwear. Budget for three and treat two as a good outcome. Each round costs one to two weeks and a sample fee.

Can I skip the size set to save time?

You can, and it is the single most common cause of a bulk order that sells badly. Grading errors are invisible on a single sample and only appear when the full size run reaches customers.

Who owns the tech pack?

You do, and you should keep a copy. A tech pack that lives only in a factory file cabinet makes it hard to move production or run a second source, and second sourcing is your main commercial protection.

Working through a first order and want a second opinion on your tech pack before sampling starts? Send us your brief and we will come back with a feasibility opinion within two working days.

Payment Terms With an Apparel Manufacturer: Deposit, Balance and What Actually Protects You
Choosing Between Full Package and CMT Manufacturing for Apparel